Skip to main content
Case Study 01

Jeddah Landfill Leachate Treatment Plant Rehabilitation

Rehabilitating a Complex 500 m³/day MBR-RO Treatment System

location_on
LOCATION
Jeddah, Saudi Arabia
business
CLIENT
Al Yamama Company for Trading and Contracting
Hero Banner

Project Overview

Green Dimension was engaged to assess and rehabilitate a 500 m³/day landfill leachate treatment plant at Wadi Al-Asala in Jeddah. The facility incorporates a complex multi-stage treatment train combining chemical conditioning, clarification, biological treatment, membrane bioreactor technology, filtration and reverse osmosis.

Green Dimension completed a structured condition assessment, identified failures across mechanical, electrical, instrumentation and membrane systems, and executed a sequenced maintenance, repair and rehabilitation program. The work was delivered under successive work orders, with commissioning and operational testing preceding final handover.

water_drop

500+

m³/day
Plant Capacity

checklist

57

Tasks
Rehabilitation Program

settings_suggest

8+

Systems
Fully Rehabilitated

verified

100%

Operational
Commissioned

The Treatment Challenge

Landfill leachate is one of the most difficult wastewater streams to treat. It is formed as water passes through deposited waste and carries dissolved and suspended contaminants into a concentrated liquid stream. Its composition can vary significantly over time and may include high organic loading, ammonia, suspended solids, dissolved salts, metals and other difficult-to-treat constituents.

At the Wadi Al-Asala landfill in Jeddah, a dedicated 500 m³/day leachate treatment plant had experienced extensive deterioration across its process, mechanical, electrical, instrumentation and membrane systems. A previous technical inspection had identified the facility as largely non-operational, requiring more than routine maintenance or isolated equipment replacement.

Al Yamama Company for Trading and Contracting, acting in connection with the Jeddah Municipality landfill facility, engaged Green Dimension to provide the technical assessment and engineering support required for a structured maintenance, repair and rehabilitation program.

account_tree Documented Treatment Train

01 Raw leachate lifting and transfer
02 Oil & Floating Removal
03 Chemical Conditioning
04 Coagulation/Flocculation
05 pH Adjustment
06 Lamella Clarification
07 Flow Equalisation
08 Anoxic Biological Treatment
09 Aerobic Biological Treatment
10 MBR Treatment
11 Multimedia Filtration
12 Cartridge Filtration
13 Reverse Osmosis
14 Sludge Handling and Dewatering
15 Chemical Cleaning & Membrane Maintenance

Structured Condition Assessment

Green Dimension began with a stage-by-stage condition assessment covering the complete treatment process. The purpose was not only to identify damaged equipment, but also to understand how failures interacted across the plant.

The assessment reviewed:

  • Mechanical equipment
  • Pumps and transfer systems
  • Chemical dosing systems
  • Air blowers and diffuser systems
  • Biological treatment equipment
  • MBR modules and membrane-scouring systems
  • Reverse-osmosis pumps and membranes
  • Process instrumentation
  • Electrical systems
  • Control and automation functions
  • Sludge-management systems
  • Civil structures and protective coatings

For example, unreliable flow readings can prevent effective dosing control. Inaccurate pH or oxidation-reduction-potential measurements can affect chemical and biological treatment. Inadequate aeration can destabilize the biological process, while membrane fouling or damaged modules can reduce filtration performance and increase the load on the reverse-osmosis stage.

This systems-based assessment allowed Green Dimension to distinguish isolated equipment faults from wider process-control and integration issues.

Rehabilitation Planning

Following the assessment, Green Dimension developed and executed a structured maintenance, repair and rehabilitation program comprising 57 defined tasks, programmed over approximately six months.

The program addressed the plant as an integrated process rather than a collection of independent assets. Key workstreams included:

Mechanical Systems

  • Check Lift and transfer pumps
  • Check Chemical dosing pumps
  • Check Air blowers
  • Check Diffuser systems
  • Check Sludge-transfer equipment
  • Check High-pressure RO pumping
  • Check Filtration equipment
  • Check Valves, piping and associated components

Membrane Systems

  • Check MBR module assessment and replacement
  • Check Membrane-scouring restoration
  • Check RO membrane and pressure-vessel inspection
  • Check Cartridge and multimedia filtration
  • Check Clean-in-place systems
  • Check Membrane-compatible chemical support

Instrumentation and Controls

  • Check pH measurement
  • Check Oxidation-reduction-potential monitoring
  • Check Dissolved-oxygen monitoring
  • Check Conductivity measurement
  • Check Flow measurement
  • Check Level instrumentation
  • Check Dosing controls
  • Check Process alarms and operating logic

Civil & Protective Works

  • Check Concrete and structural repairs
  • Check Protective coating restoration
  • Check Corrosion-affected areas
  • Check Equipment foundations repair
  • Check Pre-commissioning inspections
  • Check Instrument calibration & control-loop verification
  • Check Sequential process start-up
  • Check Process stabilization & operational monitoring

Restoring the Multi-Barrier Process

The rehabilitation strategy was built around restoring each treatment barrier in the correct sequence. The rehabilitation sequence first restored the preliminary and chemical stages to provide stable feed conditions for biological treatment. Coagulation, flocculation and clarification reduce suspended material and condition the wastewater before biological treatment.

The biological process then addresses biodegradable organic matter and nitrogen compounds through anoxic and aerobic treatment. The available process documentation describes operation with oxidation-reduction-potential control in the anoxic stage and fine-bubble aeration in the aerobic stage.

The restored MBR stage provides biological solids separation and membrane filtration before the treated stream proceeds through multimedia and cartridge filtration. Reverse osmosis then functions as the final advanced polishing barrier.

Restoring the plant required coordinated attention to:
Check Hydraulic balance
Check Chemical dosing
Check Biological stability
Check Aeration performance
Check Membrane integrity
Check Solids management
Check Instrument reliability
Check Control-system logic

This sequence reduces the risk of rehabilitating downstream equipment before upstream conditions are capable of supporting stable operation.

Equipment and Technical Supply

Green Dimension’s role extended beyond assessment and planning to include engineered equipment supply, process restoration, site implementation and recommissioning. The project records include successive work orders covering engineered spare parts, MBR and RO components, dosing systems, instrumentation and treatment chemicals used during the rehabilitation program.

Equipment and component selection must account for the aggressive nature of leachate, the process duty, compatibility with existing systems and the operating requirements of the treatment plant.

This integrated scope is particularly important for ageing treatment plants where failures have developed across multiple disciplines.

Current Project Status

Green Dimension delivered the rehabilitation under work orders issued from September 2023, with additional works ordered in November 2024. Commissioning and operational testing precede final handover.

During commissioning and operational testing, the complete treatment system is operated and monitored to verify process stability, equipment performance, control-system functionality and treatment consistency. The results will support final optimization, performance confirmation and formal handover to the client.

Project Significance

This project demonstrates Green Dimension’s ability to diagnose and rehabilitate advanced wastewater-treatment infrastructure rather than simply replace isolated equipment.

The Wadi Al-Asala plant combines physical, chemical, biological and membrane processes within one treatment train. Restoring such a system requires the ability to understand interactions between wastewater characteristics, process chemistry, biological performance, mechanical reliability, membrane condition, instrumentation and control logic.

The engagement also illustrates the strategic value of treatment-plant rehabilitation. Where the underlying process infrastructure remains recoverable, a structured rehabilitation program can restore the value of an existing asset without requiring complete plant replacement.

For landfill operators and municipal authorities, reliable leachate treatment is essential to controlling one of the principal environmental risks associated with final waste disposal. The project therefore sits at the intersection of waste management, industrial wastewater treatment and environmental protection.

Project Highlights

500 m³/day

Landfill leachate treatment plant capacity

Full Train Assessment

Structured assessment of the complete treatment train

57 Tasks

Maintenance, repair and rehabilitation program

Multi-Stage Treatment

Chemical, biological, MBR, filtration and RO stages

Comprehensive Rehab

Mechanical, electrical, instrumentation and membrane

End-to-End Support

From parts supply to commissioning and handover

Start with Your Water Analysis

Facing an Underperforming or Non-Operational Treatment Plant?

Green Dimension provides condition assessment, process troubleshooting, rehabilitation engineering, equipment replacement and recommissioning support for complex water and wastewater treatment facilities across Saudi Arabia.

Discuss Your Requirements

English العربية