Integrated Renewal of Institutional Sewage Treatment Plant with Tertiary Filtration & Reuse
Green Dimension was appointed as the contractor for the rehabilitation of critical wastewater-treatment infrastructure serving a Ministry of Defense facility in Al-Kharj.
The project covered the complete process, mechanical, electrical, automation and civil scope required to renew an aging institutional sewage treatment plant and restore it to reliable operation. The rehabilitation integrated sewage lifting, preliminary screening, aerated biological treatment, sludge handling, tertiary filtration, chlorine disinfection and treated-water pumping for landscape irrigation.
All principal equipment has been supplied and installed. Commissioning of the control systems and the remaining supporting civil works are in progress.
Full System
Rehabilitation
Paired Units
Redundancy
Automated PLC
Motor Control
Irrigation Water
Effluent Reuse
Institutional wastewater-treatment plants must operate continuously while managing changing hydraulic and organic loads. At facilities supporting essential government operations, system reliability is particularly important.
The existing plant required more than isolated equipment replacement. Its process units, pumping systems, sludge-management line, tertiary treatment, electrical infrastructure, automation and civil assets needed to be rehabilitated as one integrated system.
Green Dimension therefore approached the project as a complete treatment-plant renewal, coordinating each discipline under a single integrated delivery structure.
Green Dimension held single-point responsibility for the complete rehabilitation program, coordinating treatment equipment, pumping systems, controls, electrical works, piping and civil improvements within one integrated delivery scope.
Scope includes:
This integrated structure allowed all technical workstreams to be sequenced and coordinated through one accountable project team.
Reliable biological treatment depends on consistent sewage lifting, aeration and sludge transfer. Green Dimension rehabilitated the principal mechanical systems supporting each stage of the process.
Tsurumi submersible pumps and aerators were utilized for lifting and aeration duties. Tertiary filtration features automated pressure sand filters, followed by an EMEC chlorine-dosing system for final polishing.
The rehabilitated plant includes treated-effluent recovery for landscape irrigation. Following biological treatment, tertiary filtration and disinfection, the treated water is transferred through a dedicated irrigation pumping system using Grundfos vertical multistage pumps.
The reuse architecture converts treated wastewater from a disposal obligation into a practical resource for the facility.
Delivering a multidisciplinary rehabilitation project within an operating Ministry of Defense facility required careful coordination of access, safety, installation sequencing and operational continuity.
Mechanical, electrical, process and civil works were carried out around existing infrastructure with controlled site access, detailed work planning, and safe equipment isolation.
All principal equipment has been supplied and installed. Green Dimension is currently carrying out commissioning of the control systems and integrated treatment system.
Supporting civil works are being finalized separately, followed by final operational handover.
This project demonstrates Green Dimension’s ability to rehabilitate institutional wastewater infrastructure as a complete operating system rather than a collection of individual equipment items.
Green Dimension coordinated the complete renewal and integration of the plant under one accountable integrated scope, taking the client from aging infrastructure toward an automated and reuse-enabled treatment system.
The engagement combines biological treatment, mechanical rehabilitation, sludge management, tertiary filtration, disinfection, PLC automation, and treated-water reuse.
Integrated rehabilitation for Ministry of Defense in Al-Kharj
Single-point accountability for process, mechanical, electrical & civil scope
Complete process renewal with sludge stabilization
Automatic sand filters & EMEC chlorine dosing system
Critical pumping & aeration duties supplied in paired units
Grundfos multi-stage pumping system for landscape irrigation
Green Dimension provides condition assessment, process rehabilitation, equipment integration, automation, commissioning and treated-water reuse solutions across Saudi Arabia.